A shiploader cannot simply be switched off for maintenance. Seachios® crews clean booms, galleries, chutes, portals and conveyors with 500-bar water jets and by hand, in the hours the terminal can release them. One loader at the Port of Itaqui took ten night shifts and 630 man-hours, with no accident, no environmental incident and no export delayed.

500 bar
hydrojetting on the large surfaces
10 nights
for one shiploader, exports kept
630 h
on that job, with zero incidents
Handed back every shift
Commitment

01The drawing

The shiploader, under cleaning. Turn it, pick a part.

A slewing shiploader parked along its pier for a night’s work: rails 14 m apart, the chute 27.8 m from the slewing centre. Lifts wash the boom and the chute, the electrics are wrapped before any water and the wash is contained at the pier’s edge.

02Overview

Shiploader and industrial cleaning for ports and terminals in Brazil

Cargo dust, spillage and salt build up on a shiploader’s boom, galleries and chute. They add weight, hide corrosion and foul the moving parts. Seachios® removes them with high-pressure water and by hand, treats the steel that comes to light and takes every residue away, on shiploaders, their trippers and conveyors, transfer towers and other large steel structures.

Terminal operators, port authorities and industrial plants book us to keep the asset working: the job is planned round the berth’s programme, at night when the day belongs to loading, and the machine is handed back each morning clean, dry and protected.

03Scope of work

Industrial Cleaning. What our teams do on the machine.

Shiploaders, conveyors and large port and industrial structures cleaned by hydrojetting and by hand, in the hours the terminal can release them.

  • 01

    Hydrojetting of booms and structures

    Water jets at 500 bar take built-up cargo, dust and scale off booms, portals, towers and bogies, from the quay or from a lift basket.

    • Booms, portals and bogies
    • From the quay or a lift basket
  • 02

    Hand cleaning where no jet can reach

    Galleries, walkways, cable trays and the confined corners of the slew deck are cleaned by hand, under work-at-height and confined-space controls.

    • Galleries and cable trays
    • Confined and elevated zones
  • 03

    Isolation and asset protection

    Electrical panels, sensors, drives and conveyor belts are isolated and covered before any water is used, then checked with the terminal at hand-back.

    • Panels and sensors
    • Belts covered
  • 04

    Rust treatment and waste control

    Exposed steel is de-rusted and given a local anti-corrosion treatment, while residue and wash water are contained, segregated and sent to licensed treatment.

    • Local anti-corrosion treatment
    • Licensed treatment

04Who it serves

For terminals, port authorities and industrial plants.

Choose your role to see what you need from the service and what we deliver.

What you need

A loader cleaned and protected without losing a shift of loading.

What we deliver

  • Work planned in the hours the machine can be released, at night if the day belongs to loading
  • The loader handed back for each day’s programme, clean, dry and with its electrics checked

05How it works

From the first message to the hand-over.

The same five steps in every port, each with its own record.

  1. 01

    Asset and window

    Send the machine, the cargo it handles, its condition and the hours it can be released.

  2. 02

    Inspection and plan

    We inspect the structure and write the plan shift by shift: areas, methods, access, isolation and waste.

  3. 03

    Approval and permits

    The plan goes to the terminal and the port authority; permits and isolations are agreed before the first shift.

  4. 04

    Cleaning by shifts

    Jetting, hand cleaning and rust treatment in each window, the machine handed back for the day’s loading.

  5. 05

    Hand-over and report

    A final inspection with the terminal, the waste records and the report with photos.

06Standards & documents

The rules we follow, the records you receive.

01Standards & compliance

NR-35 · NR-33
Brazilian rules for work at height and confined spaces, applied to every lift, gallery and chute entry.
Port authority approval
The work plan is presented to the port authority and approved before the first shift.
Permit-to-work and isolation
Each shift opens with the terminal’s permit and the machine’s electrics isolated before any water is used.
Environmental control
Residue, dust and wash water never reach the berth, the drainage or the bay: they go to treatment approved by the port.

02Documents delivered

Shift-by-shift work plan
Areas, methods, crews and release hours for each shift, agreed with the terminal before work starts.
Before-and-after photo set
Every area photographed before, during and after the cleaning.
Waste records
Proof of where the residue and the wash water were taken and treated.
Completion report
The scope done, the man-hours, the steel treated and any defect found on the way.

Fig. 02 · Shiploader in plan · rails, slewing centre and reach

Fig. 03 · Telescopic chute and spout · washed from a lift basket

08FAQ

What clients ask before they book.

01Can a shiploader be cleaned without stopping the terminal?

Yes. The work is planned in the hours the machine can be released, usually at night, and the loader is handed back clean and dry for the next loading. At the Port of Itaqui one loader was cleaned in ten consecutive night shifts while the daytime exports went on.

02Which equipment and structures do you clean?

Shiploaders and their trippers, conveyors and galleries, transfer towers, chutes, portals and bogies, and other large steel structures in ports and industrial plants.

03How is a shiploader cleaned?

High-pressure water at 500 bar takes the bulk of the deposits off the large surfaces. Where a jet cannot reach or must not be used, the team cleans by hand. Exposed steel is then de-rusted and given a local anti-corrosion treatment.

04How do you protect electrical panels, sensors and belts?

They are isolated and covered before any water is used, and checked with the terminal when the machine is handed back.

05What happens to the residue and the wash water?

They are contained at source, segregated and sent to treatment approved by the port. Nothing is left to run to the berth, the drainage or the water.

06How do I request a proposal for an industrial cleaning?

Tell us the asset, the access and the hours it can be released. Our operations hub answers around the clock with feasibility and a proposal.

Technical specificationIndustrial Cleaning

Technical Specification

Scope of Services

  • Shiploaders: boom, counterweight, slew deck, portal, bogies, galleries and telescopic chute.
  • Trippers and conveyors: belt structures, idler frames, transfer points and galleries.
  • Transfer towers and chutes: internal and external surfaces, platforms and stairs.
  • Large steel structures: port and industrial structures cleaned in place, in the hours they can be released.
  • Rust treatment: rust removed from exposed steel, followed by a local anti-corrosion treatment.

Methods and Equipment

  • High-pressure hydrojetting: water at 500 bar on the large surfaces, from the quay or from a lift basket.
  • Hand cleaning: in confined and elevated zones a jet cannot reach, and beside equipment that must stay dry.
  • Access: boom lifts and the structure's own walkways, under work-at-height controls.
  • Isolation: electrical panels, sensors, drives and conveyor belts isolated and covered before any water is used.
  • Lighting: lighting towers for night shifts, so the work fits the terminal's programme.

Planning and Shifts

  • Work planned shift by shift with the terminal, in the windows the machine can be released.
  • The asset handed back at the end of each shift, clean, dry and protected.
  • Reference job: one shiploader at the Port of Itaqui cleaned in ten consecutive night shifts and 630 man-hours, with zero accidents and zero environmental incidents.

Environment and Waste

  • Residue, dust and wash water contained at source.
  • Waste segregated and transferred to treatment facilities approved by the port.
  • Nothing discharged to the berth, the drainage or the water.

Compliance and Standards

  • Operations aligned with NR-35 working at height and NR-33 confined space standards in Brazil.
  • Work plan presented to the port authority and approved before the first shift.
  • Permit-to-work agreed with the terminal for each shift.
  • Documentation includes the work plan, before-and-after photos, waste records and the completion report.
SC-REQ-01Request for serviceOperations online · Santos --:--:-- BRT

ContactOperations hub · 24/7

Need Industrial Cleaning in a Brazilian port? Our operations hub replies 24/7.

Send the vessel, the port and the dates. We reply with a plan, a team and a timetable.

Response
30–60 min
Ports
13 · 04 Regions
Operations hub
Santos · 24/7

What to send

  1. 01The vessel and its IMO number
  2. 02The port, the berth or anchorage, and the dates
  3. 03The service, and what the work involves
  4. 04A plan from one of our tools, if you made one